In brief
It is ready if every critical item has its strategy by failure mode, and if that strategy already has the data shape the ERP system needs. That means the hierarchy, criticality, task lists, spare parts lists and failure catalog. You check it in seven steps, prior to loading. If you check afterwards, the ERP schedules the same as the old one.
Why review the strategy before loading it into the ERP system?
Because the ERP schedules whatever it receives. If it receives a reactive strategy or one copied from the manufacturer, it runs it as is, and reactive work moves into the new system.
- >55%of an average facility's maintenance resources go to reactive work.DOE/FEMP (2010)
- 44%of mine production cost was maintenance, across six Chilean open-pit copper mines.Knights and Oyanader (2005)
- 3.3 timesmore downtime in the 25% most reactive plants than in the 25% least reactive.NIST (2020)
- 89%of the aircraft components studied had no wear-out zone.Nowlan and Heap (1978)
The review becomes urgent at three moments. When the company issues a corporate maintenance standard, when it changes or implements its ERP system, and when new equipment arrives or a new plant approaches the start of operations.
In all three cases there is a date that will not move, and the temptation is to load what exists. The problem is that what exists usually has gaps the ERP system does not forgive. According to Hodkiewicz and Ho (2016), historical work orders for heavy mobile mining equipment frequently have missing or incorrect functional locations, failure modes, actions or status.
The cost of staying reactive, with each figure and its source, is in the data report on reactive maintenance.

How do you check, step by step, that the strategy is ready?
With seven steps, in this order, because each one uses what the previous one left. An experienced team can apply them on its own.
1. Set what you compare against
There are two references. The first is the corporate maintenance standard or, if the company has none, a recognized framework such as ISO 55001. The second is the ERP system it will be loaded into. What ISO 55001 requires, and what it does not, is in the ISO 55001 comparison. The standard sets the method requirements, and the ERP system sets the data structure. Without a fixed reference, each area reviews against its own habits.
2. Review the asset register and hierarchy
Every item that exists in the field has to be in the register, with its place in the hierarchy and its equipment class. ISO 14224:2016, confirmed in 2022, helps here: it defines an equipment taxonomy, failure modes and a minimum data set for failures and maintenance. A poorly built hierarchy drags into the task lists, the notifications and the failure analysis.
3. Review criticality
Criticality says which items deserve more analysis and which failures are acceptable. Check that it has a written method, a risk matrix approved by operations and a date. A criticality that operations never approved gets argued at every shutdown.
4. Review the strategy by failure mode
Each critical item needs its strategy by failure mode. It says which task prevents or detects each failure, how often and why. According to Nowlan and Heap (1978), 89% of the aircraft components they studied had no wear-out zone, so an age limit would not have improved them. These are aviation data, not mining data, but they show why a strategy made only of time-based replacements leaves failures uncovered.

5. Review the plan, the task lists and the spare parts lists
The maintenance plan and task lists have to come from the strategy, task by task. The spare parts lists have to cover every task list and every failure mode of the critical items. A task list that nobody can trace to a strategy cannot be defended when operations asks for cuts.
6. Compare it with what the ERP system needs
The ERP system does not receive a report. It receives data with a structure. The table summarizes what a typical ERP asks for and what is usually missing.
| The ERP system needs | The strategy usually brings | What to check |
|---|---|---|
| Functional locations and equipment, with their class | A list of equipment from the project or the inventory | The full hierarchy, the equipment classes and a unique code per item |
| Criticality as a data field for each item | Criticality in a separate spreadsheet | That the value is on each item and feeds the notification priority |
| Plans and task lists with tasks, frequencies and durations | Task lists in documents, often copied from the manufacturer | Each task with its frequency, duration, trade and whether it needs a shutdown |
| Bills of materials per item | Manufacturer spare parts lists | The materials master codes and the stock of critical spares |
| Failure catalog: part, mode, cause and action | Failure modes in the analysis, without codes | Codes so the notification records the failure mode |
| Notification priority rules, from P1 to P4 | A habit of the area | A written rule linking notification priority with criticality |
| Indicators with their source | Indicators in a monthly report | That each indicator is calculated with data from the ERP system itself |
7. Set the indicators and measure again
The strategy holds if someone measures it after the load. Set the performance and continuity indicators that management will see, with their baseline, and measure again at three and six months. The two tables in the indicators section are a starting point.
A typical example: the seven steps on a conveyor belt
Illustrative example
A concentrator plant will change ERP systems in six months. The reliability lead picks the conveyor that feeds the mill to test the method before rolling it out.
Steps 1 and 2. The reference is the corporate standard and the structure of the new ERP system. In the register, the conveyor appears as a single item, without pulleys, motor, gearbox or belt as components.
Step 3. Criticality exists, but in a four-year-old spreadsheet that operations never approved. It is reviewed with the plant superintendent and becomes a data field on the item.
Step 4. The strategy has time-based replacements for the belt and the gearbox. It does not cover misalignment or idler wear, which are the failures that stop the conveyor most often according to last year's notifications.
Step 5. The task lists are the manufacturer's, and the spare parts list does not include the belt splice materials.
Step 6. The failure catalog has no codes for the conveyor, so notifications are closed as “other”.
Step 7. The baseline is the share of conveyor notifications closed without a failure mode. It is measured again after three months.
This example was built to show the method. It is not a client case.
With one item reviewed, the method extends to the other critical items, starting with the highest-risk ones.
What signs show that the strategy is not ready?
The ERP system itself and the maintenance meetings show them, well before any audit. If two or more of these signs appear, do the full review before the loading date.
| Sign | What it usually means | Method step that fixes it |
|---|---|---|
| Task lists repeat the manufacturer's manual | The strategy was not built by failure mode or for the operating context | Step 4 |
| Notifications are closed without a failure mode, or with “other” | The failure catalog does not exist or does not work for recording | Steps 4 and 6 |
| Notification priority is negotiated at every meeting | There is no written rule linking priority with criticality | Steps 3 and 6 |
| Nobody knows where a frequency came from | The reasoning behind each decision was never written down | Step 4 |
| Critical spares are ordered once the equipment has failed | Spare parts lists do not cover failure modes or set stock levels | Step 5 |
| Criticality lives in a spreadsheet nobody updates | Criticality is not a data field in the ERP system | Steps 3 and 6 |
| Schedule compliance is calculated outside the ERP system | The indicators have no source in the ERP system itself | Step 7 |
| One person knows more about an item than the ERP system | The knowledge of that item is at risk | Steps 4 and 7 |
The last sign has its own method, in “What does maintenance lose when a specialist retires?”.
Which indicators show whether the strategy works after the load?
Performance indicators show whether work has stopped being reactive, and continuity indicators show whether the operation can withstand a departure or a disruption. For defining maintenance indicators, the European reference is EN 15341:2019+A1:2022.
| Indicator | Reference value | Best performers | Source and scope |
|---|---|---|---|
| Share of reactive work | Over 55%; 45.7% in manufacturing | Under 10% | DOE/FEMP (2010), U.S. facilities; NIST (2020), U.S. manufacturing, 2016 data |
| Share of predictive maintenance | 12%; 17.3% in manufacturing | 45% to 55% | DOE/FEMP (2010); NIST (2020) |
| Planned maintenance on mining equipment | Drills 35%, shovels 56%, trucks 44% | Low by world standards, according to the authors | Knights and Oyanader (2005), six Chilean open-pit copper mines, 2001 data |
| Maintenance cost as a share of replacement asset value | No public average | Under 3% | SMRP (2018), any industry |
| Unplanned downtime | 3.3 times more in the 25% most reactive | The 25% least reactive | NIST (2020), U.S. manufacturing |
| The references come from different industries and years. They help place an operation, not set its target. Data reviewed as of November 12, 2026. | |||
Continuity indicators have no public reference. They are VSC's reading, and they show whether the strategy withstands what does not depend on maintenance.
| Indicator | What it shows | How to read it |
|---|---|---|
| Critical spares with a single qualified supplier | Dependence on a single source of supply | Share of critical spares with one supplier, versus those with several options |
| Inventory of critical supplies | How long the operation holds out if supply is cut | Days of operation covered by stock |
| Procedures up to date | Whether what is written follows what is done | Share of procedures updated in the last 12 months |
| Key positions held by a single person | The risk of losing knowledge | Positions with one person, versus those with trained backups |
| Production recovery time | How long the operation takes to recover after a disruption | Estimated time after a 30, 60 and 90-day access disruption |
| VSC's reading. Each operation sets its own baseline and target. | ||
Download
The strategy checklist
It includes the seven steps as a checklist and the table of what the ERP system asks for. It also includes both indicator tables, in a spreadsheet to fill in with your operation.
When does it make sense to ask for outside help?
When your own team lacks the time or the method for the seven steps, or when the loading date leaves no margin. If the team has both, doing it in-house is best.
| With your own team | With outside support by the hour | With an external diagnostic with deliverables | |
|---|---|---|---|
| When it makes sense | There is a written method, time and a dedicated person | There is a method, but capacity is short in some steps | Method or time is lacking, or the loading date is close |
| What you get | The review and the learning stay in-house | Specialist hours in the steps you choose | The gaps against the standard and the ERP system, with the steps to close them |
| What you risk | That the review competes with day-to-day work and slips | That the reasoning behind each decision leaves with the specialist | That the result stays in a report unless you require otherwise |
| What to require | An end date and an owner for each step | The written reasoning behind each decision | Deliverables in your systems, with acceptance criteria |
What should remain in your organization when the external team leaves is covered in “When the consultant leaves, what should remain in your organization?”.
See where you stand
The asset management self-assessment places your operation on each step of this guide, in a few minutes.
Next step
The Maintenance Diagnostic for the Standard compares your strategy with the standard and with what your ERP system needs. It delivers the gaps, with the steps to close them, in 4 to 6 weeks.
Frequently asked questions
What is a maintenance strategy?
It is the set of decisions about how each item is looked after. For each failure mode it says which task prevents or detects it, how often and why. The plan, the task lists and the spare parts lists come from it.
What is an ERP system?
ERP stands for Enterprise Resource Planning. It is the software system that brings a company's main processes, such as finance, purchasing, warehousing and maintenance, into a single database. For maintenance, it holds the equipment hierarchy, task lists, work orders and spare parts.
How long does it take to review the strategy before a new ERP system?
It depends on how many critical items there are and how much the strategy already holds. The Maintenance Diagnostic for the Standard takes 4 to 6 weeks. It is best finished before the data for the ERP system is prepared.
Which standard helps organize failure and maintenance data?
ISO 14224:2016, confirmed in 2022. It defines an equipment taxonomy, failure modes and a minimum data set. It was born in the oil and gas industry and is used as a reference in other industries.
What if the ERP system is already live?
The seven steps still apply. Start with the notifications and work orders from the first months, which show what the strategy is missing. Load the corrections one critical item at a time, starting with the highest-risk ones.
Sources
- DOE/FEMP (2010). Sullivan, G. P., Pugh, R., Melendez, A. P., and Hunt, W. D. “Operations & Maintenance Best Practices: A Guide to Achieving Operational Efficiency”, Release 3.0, PNNL-19634, chapter 5, pp. 5.2 to 5.5. energy.gov
- NIST (2020). Thomas, D. S., and Weiss, B. A. “Economics of Manufacturing Machinery Maintenance: A Survey and Analysis of U.S. Costs and Benefits”, NIST AMS 100-34, June 2020. doi.org
- Knights, P., and Oyanader, P. (2005). “Best-in-class maintenance benchmarks in Chilean open-pit mines”. CIM Bulletin, 2005. 2001 data from six open-pit copper mines. onemine.org
- SMRP (2018). “Best Practices Metrics Workshop”, Society for Maintenance & Reliability Professionals workshop material, slide 113. pemac.org
- Nowlan, F. S., and Heap, H. F. (1978). “Reliability-Centered Maintenance”, United Airlines for the U.S. Department of Defense, AD-A066579, section 2.8, exhibit 2.13, p. 46. apps.dtic.mil
- ISO (2016). ISO 14224:2016, “Petroleum, petrochemical and natural gas industries. Collection and exchange of reliability and maintenance data for equipment”, 3rd edition, confirmed in 2022. iso.org
- ISO (2024). ISO 55001:2024, “Asset management. Asset management system. Requirements”, 2nd edition, July 2024. iso.org
- Hodkiewicz, M., and Ho, M. T.-W. (2016). “Cleaning historical maintenance work order data for reliability analysis”. Journal of Quality in Maintenance Engineering, 22(2), 146-163. doi.org
- CEN (2019). EN 15341:2019, “Maintenance. Maintenance Key Performance Indicators”, replaced by EN 15341:2019+A1:2022. Listing from the Estonian standards body. evs.ee