In brief

A mining project is ready for the next phase when its operational readiness (OR) plan meets what is required for that phase. The maturity of each domain is demonstrated with evidence, and no critical gap is left without a feasible close-out before commissioning. What is required is set by the company's corporate standard or, if it has none, by a recognized reference framework.

At the end of each phase there is a gate review, the point at which the owner decides whether the project moves to the next phase. There is one when moving from one study to the next, when approving the investment before execution and when handing the built plant over to operations. At each of those points, the question about engineering and cost usually has a good answer. The question about whether there will be an organization able to operate what is being built almost never does.

Why it matters

In my 18-year career I have seen many projects reach commissioning with the plant finished and operations unprepared. The procedures had been copied from another site, and nobody had validated the maintenance strategy against the actual equipment. There were unfilled positions and a training plan that existed only on paper. The equipment worked. The people did not know what to do when the process went out of range.

On top of that, those projects tend to reach commissioning late and over budget. According to EY (2022), 64% of 192 mining and metals projects of more than US$1 billion ran over budget, over schedule or both. According to McKinsey (2022), 41 mining projects of more than US$500 million cost on average 60% more than announced in their feasibility study. They are projects completed between 2008 and 2018. In 2014 Bent Flyvbjerg called it the “iron law” of megaprojects: over budget, over time, over and over again.

What I have learned is that the operational readiness money has to be spent in the study phases. In execution it is already too late, because by then the design is closed and the contracts are signed. What was not prepared in time shows up at commissioning, when production takes a long time to reach what the business case promised.

Ramp-up studies confirm it. MacKinnon, Mackey and McNulty (2026) gathered some 140 cases of metallurgical and chemical plants since 1998. According to them, about half did not reach design capacity within a reasonable time. According to RBC Capital Markets (2017), across more than 100 mining ramp-ups, a new mine takes on average 10 quarters to reach steady-state capacity. And according to IPA (2021), business decisions explain the success or failure of early operations more often than technical problems do.

What is done in the study phases also shows in the result. According to IPA (2025), of more than 4,500 site and sustaining capital projects, in plants across several industrial sectors, only those that arrived well defined at the investment approval had a positive internal rate of return. On its scale, these are the projects with “good” or “best practical” definition. And only 13% of those projects in the last five years started execution with that level of definition.

By the time the gap is discovered, the moment to close it cheaply has passed. That is why it pays to ask the question at the gate review, while there is still time and budget to correct course.

The method in seven steps

What follows is how I assess a project's operational readiness before an end-of-phase review. It does not require any particular tool. It requires discipline, the right people in the room and honesty when scoring.

1. Set what you assess against

Before assessing anything, you have to agree on the yardstick. In large-scale mining that yardstick is usually the corporate operational readiness standard. That standard defines which elements the program must have and what has to exist in each phase. If the company has no standard of its own, a recognized reference framework is used and it is written down which one.

With the phase, what is asked and what it is compared against change, but not how much is required. In each phase, what belongs to it is required to be complete and backed by evidence. The table summarizes what has to exist in each domain at the three most common decision points.

DomainMoving from prefeasibility to feasibilityMoving to executionBefore handover to operations
Leadership and governanceOR strategy aligned with the business, a named leader and a preliminary budget in the investment documents.Detailed OR plan approved before the investment decision, with owners and an integrated schedule.A named authority to stop start-up for lack of readiness, and open gaps handed over with a receiver and a budget.
Organization and peoplePreliminary estimate of the operations structure and headcount, with an initial recruitment strategy and training needs.Approved organizational design, competency matrix by role and a recruitment plan tied to the project schedule.Operations and maintenance staff hired, trained and with certified competence before operating without supervision.
Operations and operating modelPreliminary operations and maintenance philosophy, with documented user requirements and the expected service level.Operating philosophy approved by Operations and an approved plan to write and validate the procedures.Start-up, shutdown and emergency procedures approved, validated in the field and in use, with utilities secured.
Maintenance and asset managementInitial criticality analysis, preliminary reliability model and high-level maintenance strategy.Complete criticality analysis, approved strategies for critical equipment and an approved maintenance system plan.Maintenance processes configured in the system, workshops and tools certified, and failure analysis prepared.
Safety, environment and permitsSafety, environmental and operational risks in the project register, and a preliminary strategy for key permits.Detailed risk analysis with mitigations built into the design, and a permitting plan integrated into the schedule.Operating permits obtained, pre-start-up safety review signed and emergency drills carried out.
Commissioning and handoverCommissioning strategy defined and the handover strategy started, with acceptance criteria and the expected ramp-up curve.Plant divided into commissionable systems, a commissioning plan with owners and an approved handover plan.Handover certificate per system signed by Operations, critical punch items closed and performance tests carried out.
Contracts, supply and sparesOperations and maintenance requirements in the tender documents, third-party services mapped and a spares strategy.OR requirements in the contracts, tied to payment, and critical spares defined by criticality and lead time.Start-up spares and consumables in the warehouse and registered, suppliers mobilized and operational purchasing working.
Systems, data and cybersecurityInformation requirements for operating defined, conceptual systems architecture and cybersecurity requirements identified.Operating systems selected and specified, asset structure approved and the master data loading plan defined.Control and management systems tested and validated by users, with master data loaded and cybersecurity verified.
Change managementChange sponsor named, change impact analyzed by group and a stakeholder map with a strategy.Change management budget, communications plan and design changes assessed for their impact on OR.Staff validated in the new processes, changes under control and deferred scope accepted by the asset owner.
Finance and operating costPreliminary OR budget and estimated operating cost, both included in the business case.OR budget approved within the investment, and detailed operating cost, approved and with its range.First-year operating budget with owners, financial systems tested and sales and transport contracts in force.
Sustainability and social licenseSocial impact assessed, conflict risk with mitigation and a conceptual closure plan with its estimated cost.Agreements signed with communities, a sustainability committee reporting to the board and a closure plan in line with regulations.Community grievance mechanism operating, closure plan approved and construction demobilization agreed.
Performance and assurancePass criteria agreed before the end-of-phase review, product quality defined and previous lessons consulted.Operational targets approved and benchmarked against similar plants, and readiness verified by someone outside the OR team.Quality laboratory validated, and readiness verified in the field and by plant system, not only on paper.
Orebody and feed variabilityOperating modes for variability, blending rule and an operational owner of the geometallurgical knowledge.The same modes, blending rule and owner, now within the business case and under document control.Geometallurgical design basis handed over in the turnover dossier and loaded into the operation's systems.
Process and metallurgyA single current process basis with an owner, and grind size set as an operating condition.Same process basis and grind size, now within the business case and under document control.Process control philosophy in force and metallurgical accounting set up before the first concentrate.

The execution column includes detailed engineering, which on many projects continues after the investment decision. The handover column runs until the handover is signed.

In addition, I measure against two phases at once. What the current phase requires and is missing is a gap. What the next one will ask for goes into the plan, but does not count as a gap.

Assessing a project in study with the handover yardstick produces an alarmist and useless report. Assessing it with the yardstick of an earlier phase produces false comfort. Both things happen.

2. Gather the evidence, not the presentations

The assessment starts with the documents. I read the operational readiness strategy and plan, how the project intends to be executed and its full schedule. I also read how the project and the future operations team are organized, and the standard or framework set in the previous step.

Then come the conversations. No single person has visibility over every area, so you have to talk to operations, maintenance, human resources, supply, technology, safety and environment, commissioning and finance. And, above all, to those who will receive the plant. If the future head of operations has not seen the plan, that is already a gap.

3. Measure maturity by domain

I assess each domain of the plan on a six-level scale, from L0 to L5. I separate L0 from L1 because both are common in the early phases and they do not mean the same thing:

LevelWhat it means
L0There is nothing: no activity and no awareness of the topic.
L1The topic is acknowledged verbally, with no document and no owner.
L2There is a draft in progress, with an assigned owner.
L3The document is complete and stored where the phase requires.
L4It is approved by whoever the phase requires, with what the yardstick asks for, and it has partial or declared gaps left.
L5It is complete for its phase, with no gaps against what is required.

The domains I review are fourteen:

The last two are specific to mining. In them I do not judge the geology or the process flowsheet, but what the organization prepared in order to operate with its variability.

To score, I follow three rules. You score what exists, not what is planned. And existing is not enough: having a signed document, with a date, a title and a table of contents, does not mean it is a good document. An approved plan reaches L5 only if it is complete for its phase. When in doubt, give the lower score, because optimism is the most common error. And do not average domains too early. A project can be solid in twelve domains and weak in two, and it is those two that will decide commissioning.

4. Test real capability, not just compliance

This is the step that is skipped most often, and it is the one that matters most. A plan can have every document the standard asks for and still not leave the plant ready to operate. Being ready means operating safely, being maintainable and producing what the business case promised.

To tell one from the other, I ask concrete questions. Does the operating model match the budgeted headcount? Was the maintenance strategy built for this equipment or brought over from another plant? Does the training schedule finish before commissioning, or in parallel with it? Do the long-lead spares already have a purchase order? Has anyone planned how the new plant connects to the utilities, the tailings or the power of the existing operation without stopping it?

When the project is integrated into an operating site, that last question weighs more than almost all the others. The existing plant cannot stop so that the new one can start, and the people who will operate the new one often come from the existing one.

That is why it pays to have the people who will operate review what is being built. According to IPA (2016), in about half of the projects studied, operators found engineering or construction errors. Those projects had 11% worse operability.

5. Record the gaps and prioritize them by criticality and close-out time

Each gap is recorded with its source: what the standard asks for, what was found and what evidence supports it. A gap without a source is an opinion.

Then they are prioritized with two questions. The first is about criticality: if this is not closed, does it affect safety, the capacity to produce or the integrity of the equipment? The second is about time: how long does it take to close, and is there enough time before the milestone that needs it? If a critical gap takes eighteen months to close and only twelve are left, it is not just another gap in the register. It is a decision that has to be made today.

Long-lead equipment is the typical case. According to IPA (2015), across 270 projects, those with a 30% slip in equipment procurement had about a 40% probability of serious failure. And lead times have grown longer. According to Wood Mackenzie (2024), the average lead time for a power transformer went from about 50 weeks in 2021 to 120 in 2024.

It also pays to distinguish between gaps and design decisions. Not every difference from the standard is a failure: sometimes the project team made a well-founded decision. What should be pointed out is what is missing, not the judgment of a specialist who already thought it through.

6. Build the close-out plan and the rules for the Operations Team during the Project stage

The close-out plan turns each prioritized gap into an action, with an owner, a date and a criterion for considering it closed. Gaps that cannot be closed in time move to a formal risk acceptance, signed by whoever has the authority to accept it.

Along with the plan, the rules for the Operations Team during the Project stage are defined. It is the operations and maintenance group that joins before commissioning. That team needs to know who it reports to and what decisions it can make. Also how it takes part in engineering reviews and in commissioning, and how it escalates when the project takes resources away from it. Without those rules, the close-out plan stays in a spreadsheet.

The data support bringing that team in early. According to IPA (2022), when the team does not include operations, projects of more than US$20 million produce on average 10% less than their nameplate capacity. According to IPA (2016), finishing the operating manuals early and integrating operations from prefeasibility (FEL 2) is associated with better start-ups. And according to MacKinnon, Mackey and McNulty (2026), start-up and ramp-up usually require about three times the steady-state operations and maintenance headcount.

7. Measure again before the gate review, and decide

An assessment is a snapshot. Before the end-of-phase review, the domains that had critical gaps have to be measured again. The result is presented to the committee with a clear recommendation: move to the next phase, move with conditions or do not move yet.

The review should be a working session, not a presentation. Each criterion is assessed with evidence, each intermediate score comes with a dated plan and the decision is written down and signed. If something goes wrong later, that record shows whether due diligence was done or shortcuts were taken.

Signs that your project is not ready for the next phase

#SignWhat usually lies behind it
1The operational readiness strategy is not approved, or it was approved and nobody opened it againOperational readiness is treated as a document and not as a program
2There is no full-time operational readiness lead from feasibility onwardNobody owns the result
3The operational readiness plan is not integrated into the project master scheduleOperations milestones will slip without anyone noticing
4The future operations team does not take part in meetings or review deliverablesThe procedures that get written will not be used
5The operational readiness team has no formal access to drawings, P&IDs and specificationsWork is done on generic assumptions that do not apply to the asset
6The maintenance strategy was copied from another site with different equipmentThe plans loaded in the system do not match the real plant
7The training schedule ends after commissioning startsOperators will learn by watching the equipment fail
8Long-lead critical spares have no purchase orderThe first failure event stops the plant
9The process design basis keeps changing and procedures are written anywayThe work will have to be redone just before start-up
10There is no plan for integration with existing facilitiesCommissioning interferes with current operations
11The operational readiness budget is used as project contingencyWhen construction falls behind, readiness will be the first thing cut
12The executive sponsor changed and nobody reconfirmed the operational readiness mandateConflicts between the project and operations stop being resolved

If your project shows three or more of these signs, the question is no longer whether there are gaps. The question is which of them can be closed before commissioning.

A case

A greenfield copper project contracted its operational readiness program on time. During the first part it had an active executive sponsor, who chaired the steering committee and resolved conflicts between the project and the future operation.

Halfway through, the company's CEO changed. The successor arrived with a different mandate: reduce operating spend and reprioritize the project portfolio. The successor did not cancel the program, but stopped chairing the committee. Responsibility moved down the levels until it ended up with the project manager.

Nobody announced it, and the effect took time to show. Conflicts between areas that used to be resolved in days started to take months. The operational readiness team identified several critical gaps for the start of operations, and none was closed in time. The ramp-up ran far beyond the plan.

The cause was not the technical quality of the work. The program was left without executive backing. The lesson is that a change of leadership in the company requires reviewing the operational readiness mandate. If nobody reconfirms the sponsor, the program is exposed. That is why leadership and governance is one of the domains I measure, and why a change of sponsor is the last sign in the table.

The data point the same way. According to PMI (2017), 77% of projects at the best-performing organizations had an active executive sponsor, compared with 44% at the laggards. According to Nandurdikar and Merrow (2018), complex projects that changed project director lost, at the median, 105% of the promised net present value. Those that kept their director lost about 50%. That figure measures the change of project director, not of sponsor, and it points to the same thing: when the person in charge changes, value is lost. And according to IPA (2025), on poorly resourced projects, turnover of key team members raises cost overrun to 24%, three times that of well-staffed projects.

When to bring in outside help

An experienced team can apply this method on its own, and it should. An outside view is worth it in three situations. The first, when the team doing the assessment is the same one that wrote the plan and finds it hard to give low scores. The second, when the end-of-phase review is close and there is no time to train anyone in the method. The third, when the committee needs an independent assessment, signed by someone who answers for it.

There are three ways to do the assessment, and they do not compete with each other:

Self-assessmentInternal reviewExternal diagnostic
Who does itThe respondent, onlineThe project or operational readiness teamAn external team, with an expert who signs
How long it takes20 to 30 minutesDepends on the team and the size of the project4 to 6 weeks
What it relies onWhat the respondent declaresThe project documentsThe documents, the interviews and the evidence for each domain
What it deliversA first reading by area and where to startThe gaps against the company standardThe prioritized and signed gaps, with the decisions and the steps to close them
When it fitsBefore deciding whether anything more is neededWhen the team has method and time, and is not assessing its own planWhen the review is close, the team wrote the plan or the committee asks for an independent assessment

If you want a first reading, start with the operational readiness self-assessment: assessment.magorai.com.

At ValueStrategy Consulting we run this diagnostic before each change of phase. We compare the project's operational readiness plan with what the next phase requires. We deliver the prioritized gaps, with the decisions and the steps to close them, and a senior expert on our team reviews and signs them. The details are on the page of our operational readiness service.

Frequently asked questions

How far ahead of the gate review should operational readiness be assessed?

Far enough ahead to close the critical gaps before the review, not just to list them. In practice, that means assessing at the start of each phase and measuring again a few weeks before the review. Assessing the week before serves to document the problem, not to solve it.

What happens if a critical gap cannot be closed before the end-of-phase review?

It is decided explicitly: the milestone that depends on it is postponed, the scope is adjusted or the risk is formally accepted. If it is accepted, it comes with an owner and a mitigation plan. What should not happen is moving to the next phase as if the gap did not exist.

Who sits at the gate review and who decides?

The project owner decides, through the executive sponsor or the committee it reports to, usually the investment committee. At the table sit the sponsor, the project manager and whoever will receive and operate the plant. Finance and an independent reviewer usually join. The operational readiness lead presents the assessment with a recommendation: move, move with conditions or do not move yet. The decision belongs to the committee, not to the team that did the assessment.

How long does an operational readiness diagnostic take?

A diagnostic focused on the next end-of-phase review takes between four and six weeks, depending on the size of the project and the availability of information. For a first reading before deciding, the operational readiness self-assessment takes 20 to 30 minutes: assessment.magorai.com.

Sources

  1. EY (2022). “How better project management can boost mining's capital productivity”, February 3, 2022. ey.com
  2. McKinsey & Company (2022). Dussud, M. “Mining capital trends and the value of more rigorous Feasibility Studies”, presentation of June 21, 2022, slide 7. gowebcasting.com
  3. Flyvbjerg, B. (2014). “What You Should Know about Megaprojects and Why: An Overview”. Project Management Journal 45(2). arxiv.org
  4. MacKinnon, B. E., Mackey, P. J., and McNulty, T. P. (2026). “McNulty Curves: New Perspectives to Enable Trust, Transformation, and Technology”. Proceedings of the World Mining Congress 2026. iimp.org.pe
  5. RBC Capital Markets (2017). Lam, W., and Rollins, D. “Ramp-ups: What to expect when expecting a new mine”, September 21, 2017.
  6. IPA (2021). “Closing the Operational Performance Gap”. ipaglobal.com
  7. IPA (2025). Marton, A. “The Path to Better Site and Sustaining Capital Projects”, July 2, 2025. Published in the June 2025 newsletter, volume 17, number 2. ipaglobal.com
  8. IPA (2016). “Avoiding Early Operability Problems in Industrial Projects”, April 1, 2016. ipaglobal.com
  9. IPA (2015). “Equipment Procurement Slip on the Rise”. ipaglobal.com
  10. Wood Mackenzie (2024). “Supply shortages and an inflexible market give rise to high power transformer lead times”. woodmac.com
  11. IPA (2022). “Early Operations Integration Is Key to Meeting Production Targets in the Renewables Business”, July 20, 2022. ipaglobal.com
  12. PMI (2017). “Pulse of the Profession 2017”. pmi.org
  13. Nandurdikar, N., and Merrow, E. (2018). “Leading Complex Projects”. Wiley. Cited from H. Duhon's review in JPT, April 17, 2018. jpt.spe.org

Editorial responsibility: ValueStrategy Consulting · contact@valuestrategyconsulting.com