In brief
Review first whatever can no longer be fixed before start-up if it is wrong. That means anything with a long lead time, anything that affects safety or the ability to produce, and anything that depends on a decision in the current phase. In practice: long-lead equipment, critical roles, integration with the existing operation, permits and executive sponsorship. The rest is reviewed by sampling, and whatever was not reviewed is stated.
What decides what gets reviewed first?
Two questions decide it, asked in this order. The first is about consequence: if this is wrong, does it affect safety, the ability to produce or the integrity of the equipment? The second is about time: how long does it take to fix, and is there time before the milestone that needs it?
Anything that answers “yes” to the first and “no” to the second goes to the top of the list. A critical gap that takes eighteen months to close, with twelve left, becomes a decision for this gate review.
Supply is the clearest example. According to IPA (2015), across 270 projects, those whose equipment procurement slipped 30% against the authorized plan had about a 40% probability of significant failure: cost growth or schedule slip above 25%, or operability 25% below target. And according to Wood Mackenzie (2024), the average lead time for a power transformer went from about 50 weeks in 2021 to 120 in 2024.
What is always reviewed, even when time is short?
Six topics are worth reviewing in full on any project, because none of them can be fixed in the final weeks. The table shows why they cannot wait and what evidence is enough to call them reviewed.
| Always reviewed | Why it cannot wait | Evidence that is enough |
|---|---|---|
| Long-lead equipment and spares | Without a purchase order in time, they will not arrive for start-up. | The critical equipment list with lead times and the status of each purchase order. |
| Critical roles and start-up headcount | Hiring and training take months, and start-up needs more people than steady state. | The staffing plan tied to the schedule and the start date of each critical role. |
| Integration with the existing operation | A badly planned tie-in forces a shutdown of the existing plant. | The tie-in and shutdown plan, approved by whoever runs the existing plant. |
| Permits to operate | Without the permit in force, the plant cannot start even if it is built. | The permit list with owner, processing time and status. |
| Mandate and executive sponsorship | Without an active sponsor, conflicts between the project and operations go unresolved. | Who the sponsor is today, when they last chaired the steering committee and what was decided. |
| Operations input to engineering | Design errors an operator spots are cheap to fix before construction. | Engineering reviews signed off by operations and the comments that were closed. |
Two of those rows are backed by public data. According to MacKinnon, Mackey and McNulty (2026), start-up and ramp-up usually need about three times the steady-state operations and maintenance headcount. According to PMI (2017), 77% of projects at high-performing organisations had an actively engaged executive sponsor, against 44% at low performers.
How do you review the rest without reviewing all of it?
The rest is reviewed by sampling, against the same standard and with fewer documents. According to IPA (2016), operators found engineering or construction errors in about half of the projects studied, and those projects had 11% worse operability. So the best return comes from looking at deliverables through the eyes of the people who will run the plant.
- Pin down the decision ahead. Write down what this gate review approves and what the phase requires in each domain.
- Review the six topics in the table in full. Ask for the evidence in the third column, not a presentation.
- Pick two or three deliverables per domain. Choose the ones operations will use first, such as start-up procedures or the plans for critical equipment.
- Ask whether each deliverable is fit to operate with. Existing and being signed is not enough: it has to match the plant being built.
- Check the plan against the master schedule. An operational readiness activity missing from the schedule will slip without anyone noticing.
The full method for assessing the fourteen domains at the end of each phase is in the guide “Is your mining project ready for the next phase?”. This short review does not replace it: it is for when there is not enough time to apply all of it.
What do you say about what was not reviewed?
You say it in writing, in the same report. The committee needs to know which domains were reviewed in full, which by sampling and which were not reviewed. Otherwise a partial review reads as a complete one, and the risk moves to the next phase without anyone having accepted it.
It also helps to separate gaps from business decisions. According to IPA (2021), business decisions contribute to operability success or failure in the early years more often than technical problems do. A review that only looks at technical documents leaves out a large part of the question.
Checklist before the gate review
Frequently asked questions
How much time does a short review of the operational readiness plan need?
It depends on the size of the project and on how well the evidence is organised. What does not change is the order: first the six topics that cannot wait, then sampling, and finally a statement of what was not reviewed.
Who should carry out the review?
Someone who did not write the plan, together with the people who will run the plant. A team that assesses its own plan finds it hard to give low scores.
Is a sampled review good enough to approve moving to the next phase?
It is, if the report states its scope and the committee accepts it in writing. What does not work is presenting a partial review as if it were complete.
Sources
- IPA (2015). McClellan, J. “Equipment Procurement Slip on the Rise”, October 13, 2015. ipaglobal.com
- Wood Mackenzie (2024). “Supply shortages and an inflexible market give rise to high power transformer lead times”. woodmac.com
- MacKinnon, B. E., Mackey, P. J., and McNulty, T. P. (2026). “McNulty Curves: New Perspectives to Enable Trust, Transformation, and Technology”. Proceedings of the World Mining Congress 2026. iimp.org.pe
- PMI (2017). “Pulse of the Profession 2017”. pmi.org
- IPA (2016). “Avoiding Early Operability Problems in Industrial Projects”, April 1, 2016. ipaglobal.com
- IPA (2021). Pountney, A. “Closing the Operational Performance Gap”, December 2, 2021. ipaglobal.com