In brief

It gets approved when it arrives as a decision someone can take. The finding states what was found and on what evidence, and what happens to production, safety or cost if it is not fixed. It also states how long the fix takes against the next milestone, what the options are, and who has to decide by when. It fits on one page, and it goes to whoever has the authority to decide before the gate review.

Why does a technical finding not get decided by management?

Usually because it arrives as information, with no decision to take. The manager hears a well-explained problem, but does not know what is being asked, what doing nothing costs or when it has to be settled. So the issue stays in the minutes and never reaches the agenda.

Communication weighs on project outcomes. According to PMI (2013), ineffective communication contributes to half of the projects that miss their original goals, and puts USD 75 million at risk for every USD 1 billion spent on projects. A finding that never reaches the person who decides is one case of that.

What does a finding need to carry for someone to decide?

It needs six things, in this order. They are the same things asked of a gap at a gate review, the point at the end of each phase where the owner decides whether the project moves on.

  1. The source. What the standard requires, what was found and where the evidence is. A gap without a source is an opinion.
  2. The consequence. What happens to safety, production or equipment integrity if it is not fixed.
  3. The cost of waiting. If it stretches the ramp-up, what each month of gap costs. The calculation is in “What does each lost month of ramp-up cost a mining project?”.
  4. The timing. How long the fix takes and whether it fits before the milestone that needs it.
  5. The options. Two or three, each with its cost and timing, including accepting the risk.
  6. The decision requested. What is being asked, from whom and by when.

Timing is usually the strongest argument, because it cannot be negotiated. According to IPA (2015), across 270 projects, those whose equipment procurement slipped 30% against the authorized plan had about a 40% probability of significant failure: cost growth or schedule slip above 25%, or operability 25% below target.

How do you translate a finding into the committee's language?

You translate it into consequences the committee already measures: production, safety, cost and schedule. The technical finding does not change; the sentence that presents it does.

The same finding, put so that someone can decide
How it is said on siteHow it goes to the committee
“The maintenance strategy was copied from another site.”“The plans for the critical equipment do not match what we bought. If we start like this, maintenance will be reactive from the first month.”
“The mill spares are missing.”“The critical mill spares have no purchase order. Their lead time is longer than the time left before start-up.”
“We do not have enough people for start-up.”“The staffing plan covers steady state, not start-up. Some roles must be trained before commissioning and are not yet filled.”
“The procedures are not ready.”“The start-up and emergency procedures have not been validated in the field. Without them, start-up depends on what each operator remembers.”

Value is measured outside the company too. According to RBC Capital Markets (2017), in a sample made up mostly of single-asset miners, two years after commercial production, those with good ramp-ups outperformed their peers on the stock market by more than 40%. Those with weak ramp-ups trailed by more than 20%.

Who do you take the finding to, and when?

To whoever has the authority to decide, and before the window closes by itself. If the finding needs budget or moves a milestone, that person is usually one or two levels above the area manager.

The executive sponsor is usually the one who unblocks these decisions. According to PMI (2017), 77% of projects at high-performing organisations had an actively engaged executive sponsor, against 44% at low performers. If the project has none, that is the first finding to raise.

The best moment is before the gate review, with time left to fix the gap. If there is not enough time, the gap goes to the committee with a risk acceptance signed by someone with the authority to accept it. The method for assessing operational readiness at the end of each phase is in the guide “Is your mining project ready for the next phase?”.

Before you take your finding up

Frequently asked questions

What if my direct manager does not want to take the finding higher up?

Ask them to accept it as a risk, in writing and signed. If they lack the authority to accept it, the question moves on its own to the level that has it.

How much technical detail should go to the committee?

Enough to make the consequence clear, on one page. The technical detail goes in an appendix, in case someone on the committee asks for it.

What if there is no time to fix it before the gate review?

Take it anyway, with its options: postpone the milestone that depends on the gap, adjust the scope or accept the risk with an owner and a mitigation plan.

Sources

  1. PMI (2013). “Pulse of the Profession In-Depth Report: The High Cost of Low Performance: The Essential Role of Communications”. pmi.org
  2. IPA (2015). “Equipment Procurement Slip on the Rise”. ipaglobal.com
  3. RBC Capital Markets (2017). Lam, W., and Rollins, D. “Ramp-ups: What to expect when expecting a new mine”, September 21, 2017. Client report, cited by author, title and date. Cited publicly by Ausenco (2026), “Getting to nameplate faster”. ausenco.com
  4. PMI (2017). “Pulse of the Profession 2017”. pmi.org